How we run a job

Project controls.
In writing.

Good working relationships depend on clear information. Our approach connects field work, schedules, questions, approvals, and close-out documents, with responsibilities and reporting agreed at project kickoff.

Pre-pour inspection · structural slabPre-pour inspection · structural slab
The system

Eight controls. Named owners.

These controls guide our approach. The specific documents, responsible contacts, and reporting cadence are set for the scope and contract.

01 · Director of OperationsBaseline scheduleCrew-loaded Gantt built before mobilization: phases by CSI spec section, critical path flagged, peak-crew row, weekly update issued to the owner.
02 · President & Office ManagerBudget & WIPLine-item budget from the estimate; monthly cost-to-cost percent-complete review of labor, material, and billings against the schedule of values.
03 · Director of OperationsRFI & submittal logEvery question and every product submittal numbered, dated, and tracked to closure with the design team — required approvals tracked before the related installation.
04 · SuperintendentDaily logs & photosSuperintendent’s daily report: crew count, work performed, deliveries, inspections, weather, and photos — the record behind every pay application.
05 · PresidentChange-order controlScope changes priced and authorized in writing before the work happens. Owners see a running CO log; cost and schedule effects are made visible for review.
06 · Office ManagerCertified payroll & labor complianceDIR eCPR filed on every public works project; prevailing-wage determinations, apprenticeship, and fringe documented per contract.
07 · SuperintendentSafetyInjury & Illness Prevention Program, toolbox talks, PPE enforcement, and incident reporting on every site.
08 · Director of OperationsClose-outPunch list, as-builts, O&M manuals, warranties, conditional and unconditional lien releases, and final inspection sign-offs delivered as a package.
Workflow

From invitation to close-out.

01

Bid & buyout

Takeoffs in Bluebeam, self-perform vs. sub decision by division, RFQs to qualified subs per trade with scope sheets and a bid exception form — no gaps papered over after bid day.

02

Preconstruction

Contract review, insurance and DIR verification for every sub, letter of intent to award, submittal schedule, baseline schedule, and a kickoff with the owner and design team.

03

Construction cadence

Daily log every day; weekly owner update with schedule, two-week look-ahead, open RFIs, and CO log; monthly pay application backed by the WIP review.

04

Close-out

Punch walk, final inspections, as-builts, O&Ms, warranties, lien releases, and a closing review — then a request for your honest feedback.

Owner visibility

Shared information.
Clear next steps.

Each project runs on a Google Workspace control workbook — schedule, budget, RFI/submittal log, CO log, and daily reports in one place. We agree with owners and design teams on which records will be shared and how updates will be delivered. Plan markups and takeoffs live in Bluebeam Revu so every quantity traces back to a sheet.

  • Weekly written update, same format every week
  • Two-week look-ahead schedule
  • Every RFI, submittal, and change order in one log
Corning Library · phased occupied renovationCorning Library · phased occupied renovation
What useful communication looks like

An update you can act on.

A project update should help an owner make decisions. The outline below shows the information we aim to keep visible; the reporting format and frequency are agreed for each project.

Illustrative reporting outline — not a live project report.

01 · ProgressWhat was completedWork performed, areas affected, inspections completed, and relevant photos.
02 · Look aheadWhat happens nextUpcoming trades, deliveries, milestones, and access or service interruptions to coordinate.
03 · DecisionsWhat we need from youThe question, responsible decision-maker, needed-by date, and effect of a delayed response.
04 · ScheduleWhat changedCurrent constraints, their expected impact, and the proposed next action.
05 · Cost & scopeWhat needs approvalProposed changes and their status, kept distinct from authorized contract work.
06 · DocumentationWhat remains openRFIs, submittals, inspections, and close-out items with a named owner and follow-up date.
Subcontractor workflow

Clean scope, clean paper.

Our subcontractor directory is organized by CSI division. Every RFQ goes out with a scope sheet for that division and a one-page bid exception form — so a qualified bid gets priced correctly instead of buried. Award follows a fixed sequence: LOI, contract, insurance and DIR verification, onboarding checklist, then mobilization.

  • Trade invitations tailored to scope and availability
  • CSLB class and DIR registration verified before award
  • Lower-tier subs listed; certified payroll flowed down on public work
Framing crew · Paradise rebuildFraming crew · Paradise rebuild
CSLB License#661667
ClassificationsB · C-8
DIR Registration#1001019326
Small Business#2033595
SuretyBonded & Insured

WANT TO SEE IT ON YOUR PROJECT?

Talk with us about the updates, decisions, and documents your team needs. We can walk through a reporting approach suited to your property and project.